Referenz Flughafen in Athen

PROJECT PROFILE

New Athens International Airport

Project Period:
1998 to 2000, final inspection March 2001


Task and Scope of Delivery:
Novoferm was project coordinator and delivered in total 6,000 door units with hardware incl. installation.
The scope of delivery included fire-resistant doors, smoke proof doors, prison doors, high-pressure doors, securi-
ty doors, tube frame doors made of steel and timber (own manufacturing as well as purchased parts). With a pro-
fessional project management all deadlines and inspection dates have been met.


Project Key Data:
1995 Placing of order with consortium consisting of Hochtief, ABB and Krantz TKT
1996 Start of construction
2000 End of construction phase
2001 End of test phase and opening


Project Parties:
• “HOCHTIEF”: System Management Responsible for Planning, construction, financing and airport operation
• ÖPERATOR”: 55% Greek Republic, 45% Consortium (thereof 40% HOCHTIEF)
• 5,000 employees during the construction phase on site, 150 subcontractors


Project Challenges:
• Delivery time as from ordering partially under 2 weeks ( despite the Balkan war at that time )
• Delivery of 2 - 3 truckloads per week
• Employees on site: 6 in construction management and 30 mechanics

Novoferm - your partner for challenges on the building site !